Major project
Darlington New Nuclear: trades, pay and site clearance
Updated September 18, 2026
Status: Under construction (1 of up to 4 planned units), as of August 25, 2026
Construction has started on 1 of up to 4 planned units. Builds like this usually need pipefitters, electricians and millwrights on site.
The Darlington New Nuclear Project is at the existing Darlington site in Bowmanville, in the Municipality of Clarington, Ontario. Construction has started on 1 of up to 4 planned units. Below: where to look for work, the typical trades, hourly pay in Ontario, and the security clearance for the site.
Finding work
Check Ontario Power Generation and the contractors named on this page, including Aecon Kiewit Nuclear Partners, for job postings.
Where can you find job postings?
Werko does not track job postings for the Darlington New Nuclear Project yet.
Ask the employer whether the job includes camp accommodation or a rotation.
Site access
You need a site access security clearance to enter a protected area at a high-security site without an escort. A nuclear power plant counts as a high-security site.
The regulator’s guidance says the licence holder should check:
Your personal history for the past five years, including where you lived. If you are under 21, the check goes back to age 16.
Your criminal record, through a name check.
You may need a credit check. This depends on your position, your access to financial information and funds, or your signing authority. A credit check may also be done for a specific reason, such as personal bankruptcy or a related criminal conviction.
You also need physical proof that the licence holder has authorized you to enter. That authorization can last up to five years.
Sources5
Trades typical for a nuclear build
Steamfitter/Pipefitter
Construction Electrician
Industrial Electrician
Ironworker (Reinforcing)
Carpenter
Concrete Finisher
Welder
Boilermaker
Ironworker (Structural/Ornamental)
Industrial Mechanic (Millwright)
Instrumentation and Control Technician
Insulator (Heat and Frost)
Mobile Crane Operator
These trades are typical for this kind of project, not jobs posted at Darlington.
Hourly pay in Ontario
Hourly · Ontario · Dated November 19, 2025
| Trade | Low | Median | High |
|---|---|---|---|
| Construction MillwrightData from 2023 to 2024 | $23.00[6] | $35.59[6] | $48.50[6] |
| Construction ElectricianData from 2023 to 2024 | $20.00[7] | $34.00[7] | $50.50[7] |
| Construction Electrician, Toronto Region | $20.62[7] | $34.86[7] | $51.40[7] |
| Steamfitter-pipefitterData from 2023 to 2024 | $28.00[8] | $45.96[8] | $56.88[8] |
Ontario ticket rules are on the nuclear and uranium page.
Where construction stands
The construction licence covers one BWRX-300 reactor. It runs until March 31, 2035.
The licence has three hold points. These are stages where the work must wait for approval. At each stage, Canadian Nuclear Safety Commission (CNSC) staff check whether Ontario Power Generation (OPG) has met its commitments. The Commission must approve lifting the hold point. Someone it authorizes can give this approval instead. That work can continue only after approval.
The first hold point was lifted on March 30, 2026. Work on the reactor building foundation could then go ahead.
OPG has applied for a licence to operate the reactor. The Commission will decide after a public hearing, on a date to be announced.
The contractor AtkinsRéalis says the first unit should be complete by 2030.
How many jobs it could create
The Major Projects Office expects all four units to create 18,000 jobs per year during construction. During operation, the units should sustain 2,500 jobs per year.[2]
The Department of Finance Canada expects the project to create and sustain about 3,700 jobs per year over 65 years. Peak construction could support up to 18,000 jobs per year.[10]
These yearly forecasts cover different periods of construction and operation. They are not current job openings.
Who is building it
Candu Energy Inc., an AtkinsRéalis company, won a $450 million contract from OPG for the first of four planned small modular reactor units. AtkinsRéalis has been the project’s architect-engineer since 2023.[4]
AtkinsRéalis works alongside GE Vernova Hitachi Nuclear Energy and Aecon Kiewit Nuclear Partners.[4]
OPG selected the GE Vernova Hitachi BWRX-300 reactor in December 2021.[1]
What has happened so far
First Nations
The Darlington site is within the traditional lands and waters of the Michi Saagiig Anishinaabeg. The site falls under:
The Gunshot Treaty.
The Williams Treaties.
The Williams Treaties Settlement Agreement.
Federal and Ontario loan guarantees support about $715 million in financing. This financing would allow seven Williams Treaties First Nations to eventually own a significant minority share of the project.
Sources
- Darlington New Nuclear Project
Canadian Nuclear Safety Commission. Retrieved September 15, 2026
- Darlington New Nuclear Project
Privy Council Office, Major Projects Office. Retrieved September 15, 2026
- Letter to Ontario Power Generation regarding Regulatory Hold Point 1 – DNNP Unit 1
Canadian Nuclear Safety Commission. Retrieved September 15, 2026
- AtkinsRéalis signs new execution contract for Darlington Small Modular Reactor Project
AtkinsRéalis. Retrieved September 15, 2026
- REGDOC-2.12.2, Site Access Security Clearance
Canadian Nuclear Safety Commission. Retrieved September 15, 2026
- Wages Construction Millwright in Ontario
Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026
- Wages Construction Electrician in Ontario
Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026
- Wages Steamfitter-pipefitter in Ontario
Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026
- Commission authorizes Ontario Power Generation Inc. to construct 1 BWRX-300 reactor at the Darlington New Nuclear Project site
Canadian Nuclear Safety Commission. Retrieved September 15, 2026