Mackenzie Valley Highway: status, trades and camps

Updated September 18, 2026

No construction decision yet. The territorial government expects a final decision in 2028 for the Wrigley to Norman Wells section.

The Mackenzie Valley Highway is a proposed all-season road of about 800 km from Wrigley to the Dempster Highway south of Inuvik. The territorial government says construction still depends on assessment, approvals, funding and a decision to proceed. Some bridge and road work along the route could start sooner.

That decision depends on the environmental assessment, permits and funding. Construction, funding, the final route and permits still need approval, even if the assessment expands.

Sources234

Work that could start sooner

Some bridge and road jobs along the route can go ahead while the highway’s assessment continues. Federal funding for the last two was announced on September 8, 2026.

  • Oscar Creek Bridge: contractors were being chosen in summer 2026, and construction is expected in the 2026-27 winter.

  • Christina Creek realignment: permits and licences are under way. The process to choose construction contractors is expected in fall 2026. Construction is expected in 2027.

  • Great Bear River Bridge near Tulita.

  • A 6 km second phase of the Prohibition Creek Access Road.

Sources35

Where can you find job postings?

Werko does not track job postings for the Mackenzie Valley Highway yet.

For job postings, watch the companies that win these bridge and road contracts.

Sources3

Camps

For the Wrigley to Norman Wells section, the 2023 assessment report says camps for 40 to 70 workers will be needed. They may be in Norman Wells, Tulita or Wrigley, or at gravel pits or quarries.

Sources6

Trades and workers

The related Prohibition Creek Access Road employed 95 people at its peak, including 61 Sahtu residents. That was road work already done, not a forecast for the highway. The territorial government is studying the labour market and planning training and employment for the corridor.

Sources3

Trades typical for a northern all-season road

  • Heavy Equipment Operator (Excavator)

  • Heavy Equipment Operator (Dozer)

  • Heavy Duty Equipment Technician

  • Construction Craft Worker

  • Carpenter

  • Ironworker (Reinforcing)

  • Concrete Finisher

  • Ironworker (Structural/Ornamental)

  • Welder

  • Mobile Crane Operator

These trades are typical for this kind of road, not jobs posted for the highway.

How the highway would be built

The 2023 assessment report expects construction from Wrigley toward Norman Wells in three segments, one after another. The report estimates these construction times:

  • First segment: three years.

  • Second segment: four years.

  • Third segment: three years.

Each segment would also need about two years of preparation. When work starts and how long it takes depend on:

  • Funding.

  • Capacity to do the work.

  • Approval from regulators and the conditions of those approvals.

The Review Board is now updating what the assessment covers, because the territorial government asked to extend the route to Inuvik. The government estimates it will file its revised assessment report in March 2027. Public review and hearings come after that, with no dates set yet.

Sources6784

Who is developing it

  • The Government of the Northwest Territories, through its Department of Infrastructure, is developing the highway.[1][8][9]

What has happened

  • March 12, 2026:

    the federal government referred the highway to the Major Projects Office.[1][3]

  • June 24, 2026:

    Canada started considering whether to list the highway as a project of national interest under the Building Canada Act. The territorial government and the Major Projects Office reported this.[3][1]

  • August 14, 2026:

    the territorial government asked to extend the assessment to the route from Norman Wells to the Dempster Highway near Inuvik.[8][7][4]

Indigenous agreements

  • Sahtu Secretariat Incorporated, the Gwich’in Tribal Council and Pehdzéh Kı̨ First Nation agreed to work together on the proposed highway. The three signed a memorandum of understanding on June 5, 2026.[1]

  • The territorial government has also signed a memorandum of understanding with Sahtú Secretariat Incorporated.[2]

Sources

  1. Mackenzie Valley Highway (MVH)

    Major Projects Office, Privy Council Office, Government of Canada. Retrieved September 15, 2026

  2. Mackenzie Valley Highway

    Government of the Northwest Territories, Department of Infrastructure (the developer). Retrieved September 15, 2026

  3. $65 million funding amendment advances Mackenzie Valley Highway construction and procurement

    Government of the Northwest Territories. Retrieved September 15, 2026

  4. GNWT moves to advance full Mackenzie Valley Highway through one coordinated environmental assessment

    Government of the Northwest Territories. Retrieved September 15, 2026

  5. Mackenzie Valley Highway Project Developer’s Assessment Report: Non-Technical Summary

    Government of the Northwest Territories (Developer's Assessment Report non-technical summary, filed on the Review Board registry). Retrieved September 15, 2026

  6. Notice of Proceeding: Online Review on the scope of the Mackenzie Valley environmental assessment

    Mackenzie Valley Environmental Impact Review Board. Retrieved September 15, 2026

  7. Notice of Proceeding: Re-scoping session dates and revised draft workplan

    Mackenzie Valley Environmental Impact Review Board. Retrieved September 15, 2026

  8. Mackenzie Valley Highway - EA1213-02

    Mackenzie Valley Environmental Impact Review Board (public registry, EA1213-02). Retrieved September 15, 2026

Join the waitlist for this project

Your signup records your interest in this project. Join the waitlist for access updates. You can leave the list at any time.

Yes, email me about Werko waitlist access and invitations. I can unsubscribe at any time.