Sisson Mine in New Brunswick: status and trades

Updated September 18, 2026

Status: Not under construction, waiting on approvals or a final decision, as of August 31, 2026

No decision to build yet. Northcliff expects to decide in the latter part of 2027, with operations starting in 2030 if it goes ahead.

Sources1

Northcliff has not decided to build Sisson yet; the project is still in the planning stage before construction. It expects a construction decision in the latter part of 2027, construction taking 2 years, and operations starting in 2030. The mine site is at Sisson Brook, New Brunswick, about 60 kilometres northwest of Fredericton.

Where the work is

The site is at Sisson Brook, New Brunswick, about 60 kilometres northwest of Fredericton. Northcliff says workers would come from nearby towns and cities, so no permanent work camp would be needed.

Sources231

Job postings

Werko does not track job postings for the Sisson Project yet.

Northcliff Resources runs the project. If it goes ahead, ask the company about job openings.

Sources4

Trades and workers

Northcliff expects about 500 direct jobs during construction and about 300 during operations.

Sources1

Trades typical for an open-pit mine and processing plant

  • Heavy Equipment Operator (Excavator)

  • Heavy Equipment Operator (Dozer)

  • Heavy Duty Equipment Technician

  • Industrial Mechanic (Millwright)

  • Industrial Electrician

  • Welder

  • Steamfitter/Pipefitter

  • Instrumentation and Control Technician

  • Construction Electrician

  • Ironworker (Structural/Ornamental)

These trades are typical for this kind of mine, not jobs posted at Sisson.

What happens before a decision

Northcliff next plans engineering work to refine equipment choices, layouts and the requirements the design must meet. It also plans to arrange financing for construction and for mining equipment that must be ordered early. Northcliff must meet the conditions of its environmental approvals. This includes the extra requirements added when those approvals were extended. If it decides to build, construction is expected to take 2 years.

Sources1

Who is behind it

  • Northcliff Resources Ltd. runs the project and holds 88.5% of the Sisson Partnership.[4]

  • The Sisson Partnership, owned by Northcliff and Todd Corporation, owns the project.[4]

  • Ausenco Engineering Canada ULC led the 2026 update of the feasibility study.[1][5]

What has happened

  • 2015: New Brunswick gave its environmental approval.[1][6]

  • 2017: the federal government gave its approval after an environmental assessment.[3][1]

  • November 13, 2025:

    the federal government referred the project to the Major Projects Office.[3][6]

  • November 14, 2025:

    Northcliff announced that New Brunswick’s Department of Environment and Climate Change had approved a five-year extension to the deadline for starting construction.[7][6]

Wolastoqey agreements

  • Northcliff has had a Co-Operation Agreement with Wotstak (Woodstock) First Nation since 2017. The Province of New Brunswick also signed an Accommodation Agreement with the Wolastoqey in New Brunswick in 2017.[1]

  • The Wolastoqey Nation in New Brunswick says it is not yet clear whether the referral will significantly affect its communities’ existing agreements. The Chiefs insist on three things: follow all proper processes, meet the province’s environmental conditions, and keep the accommodations in the signed agreements in place.[6]

Sources

  1. Northcliff Announces Results of Feasibility Study Update for Sisson Project

    Northcliff Resources Ltd. (news release distributed by Cision Canada Newswire). Retrieved September 15, 2026

  2. Sisson Project (Tungsten and Molybdenum Mine)

    Impact Assessment Agency of Canada, Canadian Impact Assessment Registry. Retrieved September 15, 2026

  3. Northcliff Resources’ Sisson Mine

    Privy Council Office, Major Projects Office. Retrieved September 15, 2026

  4. Sisson Project overview

    Northcliff Resources. Retrieved September 15, 2026

  5. Northcliff Progresses with Pre-Construction Programs for Sisson Project

    Northcliff Resources Ltd. (news release distributed by Cision Canada Newswire). Retrieved September 15, 2026

  6. Sisson Mine Project

    Wolastoqey Nation in New Brunswick. Retrieved September 15, 2026

Join the waitlist for this project

Your signup records your interest in this project. Join the waitlist for access updates. You can leave the list at any time.

Yes, email me about Werko waitlist access and invitations. I can unsubscribe at any time.