Major project

North Coast Transmission Line: camps, trades, pay

Updated October 31, 2026

Status: Under construction (Phase 1), as of September 3, 2026

Clearing and road work in 2026. BC Hydro plans to award the Phase 1 line construction contract (5L064) in May 2027, a date it calls tentative. BC Hydro’s target for Phase 1 to be in service is fall 2030.

Sources452

Phase 1 construction is underway, according to B.C. The North Coast Transmission Line is a new power line in northwest B.C.. The province expects Phase 1 to be complete by mid-2030. Construction of Phase 2, which extends west toward Terrace, is expected to begin in 2027 and be complete by winter 2032.

When work starts

BC Hydro’s Phase 1 work from October to December 2026 includes clearing the strip of land for the line and building or upgrading access roads. Clearing and access work in Segments D, E and F runs into early 2027. On the Williston to Beaverly section, line relocation runs from October 2026 to October 2027. Phase 2, which runs west toward Terrace, is expected to start in 2027 and be complete by winter 2032.

Sources4521

Find job postings

Werko does not track job postings for the North Coast Transmission Line yet.

Most hiring is through contractors. Apply directly to the contractors that win project work. BC Hydro does not accept resumes for them. For jobs on BC Hydro’s own project team in Prince George and Vancouver, check BC Hydro Careers and WorkBC.

BC Hydro says it will share the names and contact information of contractors as they become available.

Sources5

Where the work is, and the camps

  • Phase 1 runs from the Williston Substation near Prince George to the Glenannan Substation near Fraser Lake. Phase 1 is a 165-km, 500-kilovolt (kV) line. The full project would add transmission lines alongside existing lines from Prince George to Terrace, and north to Bob Quinn substation.[6][3]

BC Hydro lists four project worker camps: Vanderhoof, Terrace, Telkwa and Burns Lake. It is building the Phase 1 camp at the former Canfor site near Engen, west of Vanderhoof. Construction and installation of the dorms runs from December 2026 to March 2027. BC Hydro has not said what rotation, shift length or travel allowance camp workers will get.

BC Hydro plans to move about 85 per cent of the former Site C camp to camp sites between Prince George and Terrace. That includes all 21 dormitories. BC Hydro’s October to December 2026 update says dismantling of the Site C dormitories continues until January 2027. The update also lists moving the dormitory units to the Vanderhoof camp site.

Sources4758

Trades typical for a transmission line

  • Powerline Technician
  • Industrial Electrician
  • Construction Electrician
  • Heavy Equipment Operator (Excavator)
  • Heavy Equipment Operator (Dozer)
  • Carpenter
  • Ironworker (Reinforcing)
  • Concrete Finisher
  • Mobile Crane Operator
  • Construction Craft Worker

These trades are typical for a transmission line, not jobs posted on the North Coast Transmission Line.

Pay in B.C.

Hourly · British Columbia · Data from 2023 to 2024 · Dated November 19, 2025

TradeLowMedianHigh
Welder$23.25[9]$35.00[9]$51.87[9]
Construction Electrician$20.00[10]$34.00[10]$47.49[10]

B.C. ticket rules for the compulsory trades are on the page LNG projects in B.C. So is the 2027 change for crane operators.

Sources11

How many workers

Two forecasts from B.C., for different things:

  • About 1,400 workers at peak construction, across Phase 1 and Phase 2.
  • About 9,700 direct full-time jobs at the industrial projects the line is expected to support. Those are not jobs building the line.

These are forecasts, not open jobs.

Sources1

Who is building it

  • BC Hydro is the organization behind the project.[12][3]
  • Stellat'en, Nadleh Whut'en, Saik'uz and Lheidli T'enneh First Nations say they are First Nations partners with BC Hydro on Phase 1.[8]

What has happened

  • November 13, 2025:

    the project was referred to the federal Major Projects Office.[6][3]
  • September 3, 2026:

    the federal government and its partners broke ground on Phase 1.[6]

First Nations

  • First Nations have the opportunity to co-own up to 50 per cent of the new transmission line. B.C. says work is ongoing to finalize co-ownership agreements by the end of 2026.[6][3][1]
  • BC Hydro says its partnership with First Nations includes opportunities to supply goods and services, get training and find work.[13]

Sources

  1. North Coast Transmission Line breaking ground to power economic growth

    Government of British Columbia, BC Gov News. Retrieved October 31, 2026

  2. North Coast Transmission Line

    Privy Council Office, Major Projects Office. Retrieved September 15, 2026

  3. North Coast Transmission Line construction activities

    BC Hydro. Retrieved October 31, 2026

  4. Wages Welder in British Columbia

    Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026

  5. Wages Construction Electrician in British Columbia

    Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026

  6. The 7 Compulsory Trades

    SkilledTradesBC. Retrieved September 15, 2026

  7. North Coast Transmission Line

    BC Energy Regulator. Retrieved September 15, 2026

Join the waitlist for this project

Your signup records your interest in this project. Join the waitlist for access updates. You can leave the list at any time.

Yes, email me about Werko waitlist access and invitations. I can unsubscribe at any time.