Major project
North Coast Transmission Line: camps, trades, pay
Updated September 18, 2026
Status: Under construction (Phase 1), as of September 3, 2026
Clearing and road work in 2026. Tower work is planned from summer 2027. BC Hydro’s target for Phase 1 to be in service is fall 2030.
Phase 1 construction is underway, according to B.C. The North Coast Transmission Line is a new power line in northwest B.C.. The province expects Phase 1 to be complete by mid-2030. Construction of Phase 2, which extends west toward Terrace, is expected to begin in 2027 and be complete by winter 2032.
When work starts
BC Hydro’s Phase 1 plan for 2026 includes clearing the strip of land for the line. It also includes building or upgrading access roads, bridges and culverts. It plans to start building the line itself, such as putting up towers, in summer 2027. On the Williston to Beaverly section, the new 500-kilovolt towers go up from 2028. Phase 2, which runs west toward Terrace, is expected to start in 2027 and be complete by winter 2032.
Find job postings
Werko does not track job postings for the North Coast Transmission Line yet.
Most hiring is through contractors. Apply to those companies. BC Hydro says it will post project job openings at bchydro.com/ncelectrification. For jobs on BC Hydro’s own team, check its careers page.
BC Hydro plans to share who the contractors are on its website and at public and First Nations events. It says it intends to hire local and regional workers where it can.
Sources4
Where the work is, and the camps
BC Hydro needs temporary camps in the Vanderhoof, Burns Lake, Telkwa and Terrace areas. It plans the Phase 1 camp at the former Canfor site near Engen, for up to 350 workers from 2027 to 2031. Smaller mobile camps may be needed to fill gaps. BC Hydro has not said what rotation, shift length or travel allowance camp workers will get.
BC Hydro plans to move about 85 per cent of the former Site C camp to camp sites between Prince George and Terrace. That includes all 21 dormitories. Work planned through September 2026 includes preparing the Vanderhoof camp site. It also includes taking apart the Site C units to move them.
Camps will meet Provincial Industrial Camp requirements. BC Hydro’s measures for the local area include:
A Project Worker Code of Conduct.
Searches for alcohol or drugs that are not allowed.
Training in cultural awareness, gender and cultural safety, preventing violence and sexual harassment, and addictions awareness.
Trades
BC Hydro expects these construction jobs, among others:
Powerline technicians and power cable technicians.
Electricians, welders and millwrights.
Carpenters, equipment operators, labourers and truck drivers.
Sources4
Trades typical for a transmission line
Powerline Technician
Industrial Electrician
Construction Electrician
Heavy Equipment Operator (Excavator)
Heavy Equipment Operator (Dozer)
Carpenter
Ironworker (Reinforcing)
Concrete Finisher
Mobile Crane Operator
Construction Craft Worker
These trades are typical for a transmission line, not jobs posted on the North Coast Transmission Line.
Pay in B.C.
Hourly · British Columbia · Data from 2023 to 2024 · Dated November 19, 2025
B.C. ticket rules for the compulsory trades are on the page LNG projects in B.C. So is the 2027 change for crane operators.
Sources10
How many workers
Two forecasts from B.C., for different things:
About 1,400 workers at peak construction, across Phase 1 and Phase 2.
About 9,700 direct full-time jobs at the industrial projects the line is expected to support. Those are not jobs building the line.
These are forecasts, not open jobs.
Who is building it
Stellat'en, Nadleh Whut'en, Saik'uz and Lheidli T'enneh First Nations say they are First Nations partners with BC Hydro on Phase 1.[6]
What has happened
September 3, 2026:
the federal government and its partners broke ground on Phase 1.[5]
First Nations
BC Hydro says its partnership with First Nations includes opportunities to supply goods and services, get training and find work.[4]
Sources
- North Coast Transmission Line breaking ground to power economic growth
Government of British Columbia, BC Gov News. Retrieved September 15, 2026
- North Coast Transmission Line Phase 1: Prince George to Glenannan Transmission
BC Hydro. Retrieved September 15, 2026
- North Coast Transmission Line
Privy Council Office, Major Projects Office. Retrieved September 15, 2026
- Virtual Open House, North Coast Transmission Line: Phase 1
BC Hydro. Retrieved September 15, 2026
- Canada breaks ground on North Coast Transmission Line to deliver clean power and reduce emissions
Natural Resources Canada. Retrieved September 15, 2026
- BC Hydro repurposing Site C worker camp for North Coast Transmission Line Project, bringing long-term benefits to northern communities
BC Hydro. Retrieved September 15, 2026
- North Coast Transmission Line construction activities
BC Hydro. Retrieved September 15, 2026
- Wages Welder in British Columbia
Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026
- Wages Construction Electrician in British Columbia
Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026
- The 7 Compulsory Trades
SkilledTradesBC. Retrieved September 15, 2026
- North Coast Transmission Line
BC Energy Regulator. Retrieved September 15, 2026
Related pages
- Trades jobs
- Electrician resume
- Heavy equipment operator resume
- Major projects in Canada for trades workers
- Canada Investment Summit 2026: a guide for trades
- LNG Canada Phase 2, Kitimat: status, trades and pay
- Red Chris Mine expansion: status, trades and camp
- Roberts Bank Terminal 2: timing, trades and pay
- How to get hired on a major project in Canada
- FIFO and camp work: overtime and camp tax
- How Werko checks facts