Major project
LNG Canada Phase 2, Kitimat: status, trades and pay
Updated October 31, 2026
Status: Final investment decision announced, as of September 29, 2026
Phase 2 is an expansion of LNG Canada’s operating liquefied natural gas (LNG) export plant. The Major Projects Office says LNG Canada announced the final investment decision on September 29, 2026. The plant is in Kitimat, British Columbia, on the traditional territory of the Haisla Nation.
When work could start
LNG Canada has not yet given a date for main construction to start.
Phase 2 will add two more LNG trains. These are the units that make LNG. It also includes an LNG storage tank, a condensate tank, a loading berth and larger utility and process systems.
Finding work
For news about Phase 2, check the project updates on LNG Canada’s website.
Sources7
Can you find Phase 2 job postings on Werko?
Werko does not track job postings for LNG Canada Phase 2 yet.
LNG Canada has not said whether Phase 2 workers would live in a camp or work a rotation.
Jobs and training for First Nations
The May 14, 2026 co-operation agreement aimed to support jobs and training opportunities. Its goals also included working with First Nations on the Phase 2 expansion.
Benefits for the Haisla Nation
- The Major Projects Office says the Haisla Nation is expected to see direct benefits through employment opportunities for its members.[1]
Trades typical for an LNG plant
- Steamfitter/Pipefitter
- Welder
- Construction Craft Worker
- Boilermaker
- Insulator (Heat and Frost)
- Instrumentation and Control Technician
- Industrial Electrician
- Construction Electrician
- Industrial Mechanic (Millwright)
- Ironworker (Structural/Ornamental)
- Mobile Crane Operator
- Concrete Finisher
- Carpenter
- Heavy Equipment Operator (Excavator)
These trades are typical for this kind of project, not jobs posted at LNG Canada.
Hourly pay in B.C.
Hourly · British Columbia · Dated November 19, 2025
B.C. ticket rules are on the LNG projects page.
How many workers it could need
At the peak of construction, LNG Canada expects up to 4,000 new construction jobs in Kitimat. It also expects about 2,100 jobs to build new compressor stations on the Coastal GasLink pipeline.
For Phase 1 only, the peak workforce was more than 9,400 workers on site.
What the May 2026 funding was for
On May 1, 2026, before the final investment decision, the owners approved extra funding for the remaining work. Depending on progress, the money was to go to:
- More engineering.
- Possible orders for items that take a long time to deliver.
- Agreements with First Nations.
- Final commercial terms for the pipeline and supply chain.
- Construction work at LNG Canada’s marine offloading terminal.
Separately, in March 2026, LNG Canada said new construction work at the marine terminal would start in April 2026.
Who runs it
- JGC and Fluor Joint Venture built Phase 1 as the contractor for engineering, buying goods and services, and construction.[7]
What has happened so far
September 11, 2025:
the expansion was referred to the federal Major Projects Office.[1]March 27, 2026:
LNG Canada and the Coastal GasLink pipeline owners announced an agreement to cooperate on expanding pipeline capacity. The expansion would enable Phase 2.[1]September 29, 2026:
LNG Canada announced the final investment decision on Phase 2.[1]
First Nations ownership option
MNT Investments LP has an option to buy a majority share of a company. That company will buy the future Phase 2 LNG storage tank. LNG Canada says the Phase 2 decision lets the option go ahead. MNT Investments LP brings together the economic development organizations of five First Nations:
- Gitga’at First Nation.
- Gitxaała Nation.
- Haisla Nation.
- Kitselas First Nation.
- Kitsumkalum.
Sources
- LNG Canada Phase 2
Privy Council Office, Major Projects Office. Retrieved October 31, 2026
- LNG Canada Announces Phase 2 Final Investment Decision
LNG Canada. Retrieved October 31, 2026
- LNG Canada
BC Energy Regulator. Retrieved September 15, 2026
- Enhanced Investment Co-operation Advances Efforts Around LNG Canada’s Proposed Phase 2 Expansion
Natural Resources Canada. Retrieved September 15, 2026
- Enhanced Investment Co-operation Advances Efforts Around LNG Canada’s Proposed Phase 2 Expansion
LNG Canada. Retrieved September 15, 2026
- Landmark Indigenous Equity Option Creates Potential for One of Canada’s Largest Indigenous Ownership Stakes in Energy Infrastructure at LNG Canada
LNG Canada. Retrieved September 15, 2026
- Construction
LNG Canada. Retrieved September 15, 2026
- Wages Steamfitter-pipefitter in British Columbia
Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026
- Wages Welder in British Columbia
Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026
- Wages Construction Electrician in British Columbia
Job Bank (Employment and Social Development Canada). Retrieved September 15, 2026
Related pages
- Trades jobs
- Pipefitter resume
- Welder resume
- LNG projects in B.C.: status, trades and pay
- Major projects in Canada for trades workers
- Canada Investment Summit 2026: a guide for trades
- Ksi Lisims LNG: when work could start, trades and pay
- North Coast Transmission Line: camps, trades, pay
- Roberts Bank Terminal 2: timing, trades and pay
- How to get hired on a major project in Canada
- How Werko checks facts